DIRECTORS JOINT INDUSTRY FORUM
CODE OF PRACTICE
(FICTION)
Concerning the professional
and artistic status of
Directors in Television Drama, Comedy
and Scripted Entertainment
Recommended by the UK Joint Industry Forum
for the use of broadcasters, production companies,
executives, producers, directors and agents
CODE OF PRACTICE
PREFACE
Broadcasters, Producers and Directors agree that the relationship
between them is key to the efficient making of high quality
programmes. The purpose of this Code is to build on existing
examples of good practice in defining the professional status,
treatment and working arrangements that will enable the Director
to do the best possible work within the parameters of any
fictional programme type.
The Copyright Designs and Patent Act 1988 recognises the
Principal Director as co-author and co-first owner of copyright
in a work. The essential importance of the Director’s
creative role should be reflected in the status and working
arrangements of all Directors. The role of the Director remains
the same on all types of production, although there are differences
between programmes that may affect the exercise of that role.
This Code applies to all FICTION programming, though
its day to day application will vary with different types
of production. For example, the practicalities of a situation
comedy are very different from those of a long running series
with a pre existing style, and both are different from a single
drama.
However the principles of this agreed Code should from now
on underlie all such production without exception, and courtesy,
consideration, openness and transparency should underpin all
professional relationships.
THE PRODUCER DIRECTOR RELATIONSHIP
1. Making a television programme is a team activity. The
collaborative process is at the heart of all production.
1.1 The key relationship between Director and Producer should
be based on the principles of transparency and honesty. Effective
collaboration, creative and practical, between these two is
the backbone of every successful production.
1.2 The Producer is responsible for ensuring that the programme
is delivered on time, within budget, and to the quality and
style agreed at the point of commissioning, in collaboration
with the Director.
1.3 The Director has the responsibility, in collaboration
with the Producer, for the creative and craft aspects of production,
and for inspiring a large team from pre-production through
to final grading.
1.4 A representative of the production entity, normally the
producer, should be identified as the 'Nominated Producer',
with whom primarily the Director will collaborate.
THE RIGHT TO KNOW
Clarity and openness up front can avoid
problems later.
2. A Director should only embark on a project knowing the
nature and extent of the role to be undertaken. Prior to entering
into the engagement, the Producer and/or Executive Producer
should have thorough discussions with the Director on a wide
range of issues including:-
2.1 The script and any pre-existing vision or concept including
transmission format and any other commitments agreed with
the broadcaster.
2.2 Where relevant, the programme's pre-existing house style
within which the Director may be working.
2.3 The Director's own vision and approach.
2.4 The Director’s preferred method of working and any
particular working requirements that the Director may have.
2.5 Preparation time and script delivery dates.
2.6 Casting, including any pre-cast elements (see Clause 6.1).
2.7 The intended audience.
2.8 The parameters of the production budget.
2.9 The outline schedule.
2.10 The selection of key crew members (see Clause 5.3).
2.11 Arrangements for post production, including the Director's
Cut (see Section10).
PRE-PRODUCTION
3. Maximum possible time for pre-production can bring financial
savings in production and a better quality product.
3.1 To operate efficiently the Director needs an adequate
level of support and an office space that is quiet, with phone,
desk and chair.
SCRIPT
4. The Director has responsibility for the realisation of
the script.
4.1 The Director should discuss his or her creative approach
directly with the Producer and, where appropriate, with the
Writer or Script Editor.
4.2 The Producer is responsible for delivery of the script
at the appropriate stage in the pre-production schedule.
4.3 Open, clear and direct lines of communication should be
maintained between Producer, Director and the Writer or Script
Editor, who should finalise scripts and rewrites as early
as possible to avoid negative impact on schedule, budget and
the artistic quality of the production.
4.4 Late script changes necessitated by locations, schedule,
or other factors, should be dealt with promptly by the appropriate
combination of the Producer, the Director and the Writer or
Script Editor (subject to any contractual limitations).
PRODUCTION PLANNING
5. Early in the pre-production period the Director should
discuss the following elements in detail with the Producer,
Production Manager and, where appropriate, the first AD:
5.1 The Production Budget
The more information the Producer gives the Director about
the details of the budget, the easier it is for the Director
to recommend the most effective way to spend the funds available
and to suggest ways in which cost savings might be achieved.
5.2 The Joint Industry Forum Contract Guidelines dated 1 July
2002, state:- The Director should not be required to work
within a budget with which the Director is not familiar. In
normal circumstances, a Director does not have responsibility
for setting a budget but must have the opportunity to become
familiar with the elements of the budget that will affect
them.
5.3 The extent, if any, to which a Director is accountable
for budgetary control should be a matter of specific discussion
and agreement.
5.4Warranties
Where a Director is required to sign a warranty of working
within the final production budget, he or she must have proper
access to it and sufficient control over spending.
5.5The Hiring of Creative Personnel
In co-operation with the Producer, and subject to budget limitations
and programme type, the Director chooses key crew members
such as D.O.P, Designer, first AD, Editor and Composer. Normally
both Director and Producer have right of veto on any name.
Prior to entering into an engagement, a Producer should inform
a Director of any key crew members who have already been,
or are about to be, engaged.
5.6The Production and Shooting Schedules
Although the Producer is charged with prime responsibility
for these schedules, the Director’s role is critical.
The Director should therefore have the opportunity to provide
detailed input into their formulation.
ARTISTIC PLANNING
6. In collaboration with the Producer, the Director should
at an early stage in pre-production take the lead in discussions
in the following areas:
6.1 Casting - with Casting Director.
Sometimes major casting will already be in place at the outset
of a project. However, as the Director will be working closely
with the actors to deliver the best performances possible,
he or she should have maximum possible input into the choice
of cast.
6.2 Design - with Set and Costume Designers,
Make-up and Hair Supervisors.
6.3 Cinematography - with Director of Photography.
6.4 Locations - with First AD, Location Manager,
Director of Photography and Designer.
PRODUCTION
7. All creative decisions taken in this phase will be made
by, or in consultation with, the Director.
REHERSALS
8. Pre-shoot rehearsals are normally taken by the Director
with the script supervisor and AD's in attendance, although
different arrangements may be mutually agreed. Rehearsal time
is an aid to both efficiency and quality; it helps the Director
to clarify ideas and improves actors' performances, saving
time, and hence money, on set.
PRINCIPAL PHOTOGRAPHY/RECORDING
9. The Director directs all scenes in the script or programme.
The Director should therefore be consulted on the matter of
all second unit shooting and pickups. In all normal circumstances,
the Director should have first refusal of directing any retakes
or reshoots.
9.1 The Director is in creative control of shooting on the
floor, set or location.
9.2 The Producer has overall responsibility for all management
aspects of the shooting process, including Health & Safety.
9.3 The Director conducts shooting as efficiently as possible
within the limits of the schedule and the budget.
9.4 The Producer recognises that the Director is the senior
creative person on the set.
9.5 Directors perform to the best of their creative ability
where they have freedom to undertake their work without excessive
supervision.
9.6 All notes to actors or technicians either come from or
are passed through the Director.
9.7 Script changes are sometimes needed during shooting. Any
contractual arrangements that impact upon the Director's ability
to make such changes should be discussed with the Director
prior to entering into an engagement.
9.8 The Director should normally be provided with a quiet
office space near the set to work in during the shooting day.
9.9 The Director’s working conditions affect safety
and productivity on the set. For this reason it may be that
the Director should be driven to and from the set or location
during the shooting period. This should be discussed and agreed
with the Director prior to the commencement of an engagement.
9.10 The Director has the right to see rushes, normally on
a daily basis.
POST-PRODUCTION
10. Throughout the post production process it is recognised
that although the Producer or Broadcaster has final editorial
control, the Director’s artistic contribution as co-author
of the programme has to be respected. Any particular arrangements
for the post-production process should be discussed with the
Director prior to the engagement.
10.1 The Director supervises all stages of post-production.
All such work is to be paid for.
The stages of post production are:-
10.1.1 Director's Cut.
After shooting is completed, the Director has the right to
prepare a Director's Cut. Sufficient time should be allowed
for this process, in light of the schedule and the nature
of the production. This is done exclusively with the Editor
and is shown to the Producer when ready, or after an agreed
period.
The Producer's response to the Director’s Cut is invaluable,
especially if they have not previously viewed cut material.
10.1.2 Final Cut
This is the version of the programme that is shown to the
Commissioner. It has normally been agreed between the Producer,
the Executive Producer, and the Director.
10.1.3 Music
The Director and Composer, in collaboration with the Producer,
decide the nature of the music to be written and, with the
Editor, where it will be placed.
10.1.4 Sound Effects: (ADR/Post Synching, Track Laying,
Foley)
The Director takes any ADR session with actors, and gives
detailed briefings on other sound elements. The Producer may
be involved in this process.
10.1.5 Music Recording
This is under the direction of the Composer and Director,
with the Producer normally in attendance.
10.1.6 Sound Mixing/Dubbing
This takes place under the Director's supervision. The Producer
normally attends the final mix and makes comments.
10.1.7 Grading/Telecine Transfer
This is carried out by the Director, the D.O.P. and Editor,
working with the Grader. The Producer often attends a final
transfer.
10.2 Final editorial control rests with the Producer and
the Broadcaster.
PUBLICITY AND PROMOTION
11. The Producer will rarely be solely responsible for the
promotion of a television programme. However the Producer
should ensure that press and publicity representatives are
provided with information about the Director for use in press
packs, press releases and for screenings so that the Director's
contribution is recognised at this stage. Relevant parts of
the publicity process should be discussed with the Director
in advance by the Producer and press/publicity representatives.
EXPENSES AND TRAVEL
12. Expenses should be fair and reasonable and payment should
be made in accordance with the Joint Industry Forum Contract
Guidelines which state:
12.1 The expenses guidelines operated by the engaging
company should provide for directors to be reimbursed for
expenses actually incurred including those associated with
travelling and living away from base. A director and/or their
agent shall not be precluded from raising other expenses issues
in contract negotiations, including the issue of living away
from home.
12.2 Expenses claims accompanied by receipts must be submitted
by the Director and settled by the company within a reasonable
period.
12.3 Where reference is made in the 'Deal Memo' and/or
contract to a company's 'Expenses Guidelines', these should
be supplied to the director at the time, or information given
about how to consult them.
12.4 If expenses provisions are to be varied from the
above general principles, alternative ways of meeting expenses
should be identified and agreed in the contractual discussions
and included in the contract.
CONCLUSION
13. This Code should be consulted in association with the
Directors Joint Industry Forum DIRECTORS' CONTRACT GUIDELINES.
13.1 This Code has been produced as part of an ongoing process.
The Joint Industry Forum will be responsible for reviewing
and monitoring the application of this Code and agreeing any
developments or amendments.
THE DIRECTORS JOINT INDUSTRY FORUM
This Code of Practice has been drawn up by the Status Working
Group of the Directors Joint Industry Forum. It should be
used to inform all relationships between Producers and Directors.
The following organisations are members of the Forum and
have taken part in the discussions on this Code of Practice.
Directors' Representative Organisations
The Directors Guild of Great Britain (DGGB)
Broadcasting, Entertainment, Cinematograph and Theatre Union
(BECTU)
Directors' and Producers' Rights Society (1992) Limited (DPRS)
The Personal Managers' Association (PMA)
Broadcasters/Producers
The British Broadcasting Corporation (BBC)
British Sky Broadcasting Limited (BSkyB)
Channel Four Television Corporation (C4)
Five Limited (C5)
ITV Network Limited (ITV)
Producers’ Alliance for Cinema and Television (PACT)
Sianel Pedwar Cymru (S4C)
Teledwyr Annibynnol Cymru (TAC)
|